Caltrain Firebird

Jun 14th, 2010 | Posted by

by Rafael (warning: long post)

Introduction
Caltrain Firebird is a new infrastructure and operations concept I have developed to illustrate how integrated planning and modern technology could reduce HSR implementation cost in the SF peninsula while delivering the desired aggregate throughput capacity for the corridor plus improved Caltrain service, probably at a lower operating subsidy per passenger.

Note that CHSRA had previously already planned to share track with Amtrak and Metrolink in the Fullerton-Anaheim section but returned to the concept of dedicated HSR tracks in the arguably mistaken belief that FRA regulations are immutable and, that the existing dual tracks cannot deliver sufficient capacity. For now, though, let us examine the situation in the SF peninsula in more detail.

One Caltrain board member recently suggested the entire railway may have to shutter in 2012 unless it figures out a way to deliver more bang per county taxpayer buck. That will take large capital investments, but the state and federal governments will pick up the lion’s share of those – bureaucrats tend to think in terms of which pot funding comes out of, not who is putting the money into those pots in the first place. Regardless of which level of government ends up paying for them, the capital improvements have to be cost-effective, which means they ought to be driven by a financially viable strategy for future operations.

The Caltrain 2025 plan of record assumes electrification, lightweight EMUs, signaling upgrades plus access to the new Transbay Terminal will be sufficient to double line capacity and triple ridership by that year (implies 50% more seat capacity per train). However, increasing rush-hour rail traffic from 5 to 10 trains per hour each way would snarl up motor vehicle traffic at all remaining grade crossings. IMHO, it seems unlikely that Caltrain would ever get environmental approval for doubling rush hour train frequency, absent full grade separation of the entire corridor. The only available partner for that is CHSRA, so Caltrain’s plans have to change to accommodate HSR operations.

The notion that CHSRA should work around Caltrain’s already-completed plans that for the most part predate prop 1A needs to be challenged or else, the HSR starter line may never get fully funded and neither service is going to be successful. The current threat to Caltrain’s survival in the medium term makes lateral thinking more important than ever. The two organization may well prefer working independently to being joined at the hip, but the awkward fact is they need each other. This is reflected in the Peninsula Rail Program organization they’ve set up, but IMHO that body is still focused more on resolving conflicts between existing investment plans than it is with aggressively seeking out synergies to increase value per capital investment dollar spent.

Granted, it is not CHSRA’s job to sort out Caltrain’s – or any other legacy operator’s – funding issues. Nevertheless, CHSRA very much is supposed to secure full funding for HSR while also preserving “HSR feeder” systems that its own ridership forecast depends on. In passing AB3034 via prop 1A, voters explicitly reserved some 10% of available capital improvement funds for such feeder systems, with heavy rail a priority.

CHSRA has a much better chance of securing additional federal and other non-state funding if it can demonstrate that it is actively wringing cost out of its plans wherever possible. When you ask taxpayers and private investors to cough up $35 billion, there should be ZERO sacred cows.

Here is a map to help make sense of the details discussed below:


View Caltrain Firebird in a larger map

Main Line plus Long Sidings
Firebird would replace Caltrain’s existing current baby bullet, limited and local services and, the associated timetable. As a valuable fringe benefit, it would also enable HSR service in the SF peninsula without having to construct any new tracks dedicated to that.

The brand name refers to a famous ballet about a fabled beast that is both a blessing and a bringer of doom to its owner. The former would apply to funding and to rail customers, the latter might ring true for those who own property near the line – especially in the sections that will require new tracks for Caltrain.

The concept relies on a dual track main line in the SF peninsula, with siding tracks for serving selected groups of stations. The main line would be shared with HSR via the “rule of special applicability” that FRA will anyhow need to write for CHSRA. It’s common for national regulators to draft new rules in order to enable the safe operation of technologies that are new to their jurisdiction. Indeed, FRA had already begun just such an effort for Florida HSR before voters shelved the project. It’s now live again, so FRA will presumably pick up where it left off.

There would be no “Caltrain tracks” nor “HSR tracks” north of way point Lick near the Monterey Highway in south San Jose, the southern end point of PCJPB property. There would just be a main line and a number of sidings. This implies interleaved operations based on an integrated timetable and integrated traffic management, a choreography of steel and electricity.

In the SF peninsula, the main line would have a nominal speed of 90mph where possible – up from 79mph thanks to upgraded signaling and other changes. The number is not arbitrary, as the power required to overcome aerodynamic drag is proportional to the cube of velocity. Train designs for top speeds of 125mph necessarily feature longer transmission gear ratios and hence, lower acceleration performance at low speeds.

At selected locations, Caltrain would depart onto a siding at line speed, serve two to four stations and return to the main line at the speed target for that location, at a specific time. The primary advantage of this approach is that only a fraction of the corridor needs to be quad tracked, saving a lot of cost and reducing environmental impacts related to right of way width. A lower total number of miles of track also means lower infrastructure maintenance costs and, those would be shared with the HSR operator. Exploiting a main line more aggressively is the best way to cut operating overheads.

There would be a single, proven signaling system, featuring integrated traffic management and positive train control, for the whole corridor. The technology selected should be capable of headways as short as 2 minutes, something that ETCS level 2 has made possible at a line speed of 125mph in a real-world implementation in Switzerland. Other systems might also meet this spec. CHSRA must anyhow make this investment, so there is no need for Caltrain to develop its homegrown CBOSS technology any further. IMHO, absent grade crossings, that effort boils down to consultants lining their pockets and corporate welfare for UPRR.

In practice, a two-minute headway would give timetable planners capacity for up to 30 trains per hour each way. However, any emergency situation would have to be reliably detected and acted on within around 32 seconds whenever an express train is just two minutes behind a regular one, since trains are heavy and cannot stop on a dime. That’s not as hard as it sounds, thanks to signaling and positive train control. If both trains are traveling at line speed at the time of the incident, more time is available to avert disaster.

A useful analogy is a virtual conveyor belt moving at line speed, with slots at defined intervals (the analogy does not refer to propulsion, just to timing). Any train that wants to use this belt should travel at its speed and in one of the slots. It should also maintain a distance equal to an integer multiple of the headway times the line speed relative to the front of the preceding train, regardless of whether that’s a Caltrain or an HSR train.

Taktverkehr
The core operations concept would be what Germans call Taktverkehr, roughly “traffic to a beat” or “metronome traffic”. If a train departs onto a siding, the time it must spend there is equal to the length of that siding divided by the line speed plus an integer multiple of the headway and the line speed. In plain English: to permit one train behind it to overtake, a train on a siding must “lose” 2*2=4 minutes, relative to time it would have taken to cover the same distance on the main line at 90mph. For two consecutive overtakes, it’s 6, for three it’s 8 etc. Losing just 2 minutes is not enough for even a single overtake. However, a train can stop at a station on the main line and accelerate away in time to jump back on the conveyor after slipping exactly one slot if that slot is not already occupied.

Imagine you have Caltrain A running in slot #1, an HSR (or Caltrain express) train B in slot #2 and second Caltrain C in slot #3 on the main line. Train A departs onto a siding, freeing up slot #1. Train B overtakes it while A is moving on its siding and serving stations. Train C departs onto the same siding, freeing up slot #3. At the exact moment train A reaches the end of the siding, traveling at main line speed, it recycles slot #3. Train C will later recycle slot #5 etc. In this manner, you can interleave express and certain non-express service patterns without sacrificing any line throughput at all (once you reach a steady state at the end point of the conveyor belt).

However, an express HSR train running at 125mph would need several empty slots ahead of it so it can gradually “gain” on the slower conveyor belt. Alternatively, slower trains in front of it would have to move off to a siding in a timely fashion so it can overtake them without slowing down. In the above example, Train B could speed up as soon as slot #1 becomes available.

Every slot timetable planners have to leave unused to accommodate speed mismatches translates to lost line capacity. In the particular case of the SF peninsula that’s acceptable, but only up to a point. During Caltrain’s rush hour, there might not be enough empty slots to permit many – or any – express HSR trains to run. If so, the HSR operator would either run non-stop at 90mph or else, run at 125mph but stop at HSR stations on the peninsula. Note that AB3034 specifies a non-stop line haul time of 2h40m for SF Transbay Terminal to LA, but it does not require that this performance be feasible at all times of day.

Station Selection
Given that sidings imply expensive quad tracking and high-speed turnouts, each candidate should serve stations that can be expected to contribute significant ridership. Once a year, Caltrain measures average weekday and weekend boardings for each station. Out of the 36,778 total for 2010, SF 4th & King contributed 8673, Palo Alto 3905, Mountain View 3264, San Jose 2698, Millbrae/SFO 2485 etc. There are plenty of stations that contribute low thousands to high hundreds each.

Past performance is not a perfect indicator of future performance, but there are 11 stations that each currently contribute (much) less than 1% of total ridership: Bayshore, South SF, San Bruno, Hayward Park, Belmont, College Park, Capitol, Blossom Hill, Morgan Hill, San Martin and Gilroy. The last 5 are served by just three trains a day (each way) via trackage rights on UPRR’s central coast line, not because there’s a hard capacity constraint but because there simply aren’t enough potential customers.

My proposal is to suspend or cancel Caltrain service at all of these 11 stations, which together comprise just 5% of total ridership on a service that is dwarfed by BART and regional rail providers elsewhere in the nation and world. If you’re going to cut costs by sharing core infrastructure with a service that depends on not stopping frequently, you have to make some compromises. Note that Caltrain has closed stations due to lack of ridership in the past, just not so many all at once. Gilroy is slated to get an HSR station and, Amtrak Capitol Corridor could theoretically be extended to either Hollister or Salinas.

Local transit advocates may howl at the prospect of anyone anywhere losing Caltrain service, but IMHO that would be letting the perfect be the enemy of the very good. There is only a limited amount of operations subsidy funding available, so the focus ought to be on serving the vast majority of customers better.

San Bruno Station and Curve
Note the special case of San Bruno, where Caltrain intends to spend a whopping $300 million to move the station in the expectation that this will boost ridership. The railway expended a lot of time and effort on coming up with a design that works for the local community. This is now shovel-ready and on the list of projects due to be implemented with ARRA and prop 1A funds. Unfortunately, the design predates prop 1A’s passage and preserves a sharp curve that really ought to be straightened so HSR trains don’t need to slow down before they pass it. Worse, current ridership in San Bruno is so low (370 per average weekday) that the station would be marginal even if it that number were to double. In addition, quad tracking is complicated by the presence of BART tracks stacked under the Caltrain rails.

Therefore, I recommend suspending the entire shovel-ready San Bruno project until the PRP figures out an operations plan for the whole peninsula that will make Caltrain financially viable while keeping total capital investment in the corridor within reason. The good burghers of San Bruno will not like this one bit, but just maybe the way to do this right is to discontinue service there altogether.

Rolling Stock Specifications
In addition to ridership, siding candidates should deliver reasonable dwell times at stations with aggressive but technically feasible acceleration specifications for Caltrain’s new EMU rolling stock. The average value for 0 to 90mph should be on the order of 0.6-0.7 m/s^2 to keep sidings short, line haul times low and, to provide sufficient reserves to make the timetable robust.

Longer single-level EMUs perform substantially better in this regard than shorter bi-level consists with comparable crash safety. In addition, they would facilitate harmonizing platform height to the high level that CHSRA prefers. Let’s not forget which agency will be funding the lion’s share of the corridor improvements.

For the purposes of my analysis, I picked off-the-shelf Stadler FLIRT trains as representative of the type of technology that will be required. This is not meant to be an endorsement of that particular product.

Right of Way Constraints
A related objective is avoiding quad tracking in sections where that would cost a minor fortune. High acceleration performance lets trains reach main line speed in a short distance and in some cases, avoid expensive construction measures to overcome severe lateral space constraints due to existing structures. The following list may not even be exhaustive:

  • In SF, the elevated end section of I-280 was built around the existing dual-track rail line. Its supports block the path for additional tracks near Napoleon St south of tunnel #2 and also between 22nd St and Mission Creek. This is on top of the fact that the hilly terrain already requires four short tunnels in the area.
  • In South San Francisco, the Caltrain tracks run through a UPRR marshalling yard.
  • Between San Bruno and Millbrae, BART has consumed so much of the originally available right of way that implementing quad tracking at grade will be difficult. If HSR trains are to dwell for an extended period of time to accommodate airline passengers with a lot of baggage or else, there is a desire to offer integrated baggage handling to maximize the relief HSR can bring to SFO (that was the whole point), it may even be necessary to construct an ugly tall aerial leading to platforms above the mezzanine level.
  • In San Mateo and Menlo Park, the available right of way is too narrow for quad tracking.
  • In Palo Alto, the layout of the Univ. Ave/Alma St grade separation intrudes on the railroad right of way.
  • At San Antonio Rd, ramps to Central Expressway and the Caltrain platforms mean the available ROW is too narrow for quad tracking.
  • In Mountain View, overpass supports, a VTA light rail track and busy frontage roads mean the right of way can only accommodate the already existing two tracks at grade between the 85 and 237 freeways. Unsurprisingly, the city would prefer that CHSRA to implement grade separation in a trench, but Stevens Creek near 85 presents a hydrological hazard well below grade and, grade level actually rises between Castro and that location (see Clem’s Focus on Mountain View). A viable solution must address both the vertical and the lateral constraints.
  • In Santa Clara, the right of way at grade is constrained by the junction with UPRR’s Alviso line and a marshaling yard.
  • In San Jose’s Gardner district, much like in tony Atherton further north, there has been strong opposition to quad tracking from residents near the existing line, prompting CHSRA to select the severely curved 280/87 alignment alternative, complete with iconic bridge and other cost-maximizing measures. Reversing that decision would only be conceivable with a new, less intrusive proposal.

On the plus side, Caltrain has already quad tracked a few sections of its network. Where justified by ridership considerations, those should be leveraged. Service at Bayshore should nevertheless be suspended due to low ridership. If the Brisbane Baylands development actually happens, that could easily be revisited. However, that would cost CHSRA its prime candidate for a stabling and light maintenance yard at the north end of the starter line, even though the soil there was contaminated by decades of Southern Pacific’s operations.

Siding Length and Station Count
The analysis I did yielded a mildly surprising result: the optimal siding length is 3-4 miles, with not one but two consecutive stations served for the time penalty associated with letting a single train overtake, i.e. 4 minutes with moderate acceleration requirements for the sections between the stations. This was for a target dwell time of 30 seconds, which is reasonable for level boarding of long single-level trains. Increasing the headway to 2.5-3 minutes would substantially increase dwell times, reduce speeds between stations and/or favor fewer but longer sidings containing 3-4 stations each. The latter would work out between Millbrae and Calif. Ave but less well south of Palo Alto. Additional scenarios should be analyzed to explore the trade-offs involved.

Proposed Sidings
Here are the siding sections that I propose:

  1. Millbrae-Burlingame
  2. San Mateo-Hillsdale
  3. San Carlos-Redwood City
  4. Menlo Park-Palo Alto-California Ave
  5. San Antonio-Mountain View
  6. Sunnyvale-Lawrence Expy

  • The acceleration and deceleration sections of sidings 1 and 2 approach each other to within a couple of hundred feet. Therefore, it may make sense to also connect the the two such that timetable planners have the option of keeping selected Caltrains off the main line for a three overtake scenario in support of express HSR operations. A double overtake is theoretically feasible even if all four stations were served, but it would sharply reduce the amount of timetable padding. If planners need a double overtake at a given point in the timetable, they should have that train serve any three stations and run through the fourth.
  • Siding 4 was the only case in which it made sense to group three stations rather than two. Timetable planners could decide to have a given train serve any two and achieve a single overtake scenario or else, serve all three and achieve a double overtake. Note that not all impacts can be avoided: the chicane at Univ Ave/Alma St in Palo Alto will need to go and the right of way widened a little bit in Menlo Park. However, those measures are justified by proven ridership, not supposed FRA red tape nor bureaucratic megalomania.
  • The Mtn View station on siding 5 would have to move a couple of blocks toward Shoreline Blvd to give southbound trains enough distance to accelerate to a useful line speed of perhaps 80mph at the 85 underpass. This would anyhow make sense in the context of the more extensive remodeling of roads in the downtown area that would be needed if CHSRA decided to site the mid-peninsula HSR station there. San Antonio Rd will also present problems, but at least that is not a major freeway and therefore easier to reconfigure.
  • Siding 6 leverages a section of existing quad track south of Fair Oaks Ave

Siding Implementation
In principle, siding tracks can run either outside or inside the main line. In the former case, all of the stations on that siding must have side platforms, in the latter all must have a single central island platform to keep slow traffic on the left. In addition, each individual siding requires four high-speed turnouts rated at 90mph for the curved section. If sidings 1 and 2 are connected for additional flexibility via an additional set of four switches, they must feature the same track order.

The main line should always be on the straight (or less curved) section of each switch, since as express trains need to run through at 125mph. Suitable designs do exist, but they are very long and require multiple actuators, see image below. The Firebird concept is predicated on switches that can be actuated very frequently and reliably without excessive maintenance overheads.

SF Stations and Approaches
Bypass tracks would be available at 4th & Townsend station en route to the Transbay Terminal. A high-performance design requires expensive tunneling/trenching all the way to 22nd Street, which would also separate the remaining grade crossings at 16th and Common(Berry) St. The latter is currently closed but could prove useful as Mission Bay is developed.

Crossing the Mission Creek outfall at grade, as TJPA currently assumes, would be cheaper and avoid a hydrological hazard, but the descent section toward the DTX tunnel would put the below-grade 4th & Townsend station well into that structure with just a single bypass track. This constrains the throughput of the DTX tunnel and forces planners to use 2nd instead of 3rd St for the alignment.

Instead, I propose letting the tracks cross the outfall below the culverts and excavating all of 4th & King to create a station with multiple long platform tracks plus a run-through stabling/light maintenance yard – below grade (h/t to Richard Mlynarik). This would be an expensive but inevitable consequence of putting the approach tracks below grade. My map shows four full-length active platform tracks, an optimized system design might feature a different number.

A run-through yard would be especially important if CHSRA fails to secure the Bayshore property for its stabling yard, though it is unclear how many additional trainsets Caltrain could accommodate in addition to half of its own EMU fleet. At least the HSR operator could clean the trains at 4th & King instead of at the TBT, eliminating CHSRA’s concerns about feasible dwell times at the downtown station. Note that thanks to electrification, part or all of grade level at 4th & King would become available for development or perhaps, for a new city park.

The expense of all that excavation would be partially compensated by reducing the number of tracks inside the DTX tunnel from 3 to 2, which means it can be dug using fast and cheap TBM machines. In addition, moving the run-through station out of the tunnel would mean TJPA could leverage 3rd St rather than 2nd, though that would put the DTX within earshot of the MOMA building. That in turn would permit a one-way loop track alternative to create a train box at the TBT with six dead-straight run-through tracks that would preserve main line capacity. However, those tracks would end up a little further west than is currently planned – a consideration that TJPA would have to deal with quickly because it impacts the placement of support columns for the above-ground portion of the TBT.

Note that 4th & Townsend would nominally be a Caltrain station paid for by CHSRA under the heading of ROW acquisition, subject to an easement that would let the future HSR operator leverage the platforms for a nominal fee. This is legalese sophistry but it just might get CHSRA out from under the 24 station limit in AB3034. The same – admittedly tortured – logic could perhaps apply to the mid-peninsula station.

San Jose Diridon and Approaches
In the Firebird concept, SJ Diridon would become a single-level station at grade with two main line plus four full-length platform tracks accessed via two island platforms. These would be shared by Caltrain, HSR, Amtrak and ACE, assuming platform height are compatible. Worst case, room for an additional side platform for these legacy services will have to be found. This doesn’t just translate to a cheaper station, it eliminates the need for aerials in the approaches on either side. However, it does imply that all operators, including UPRR, Amtrak and ACE, will have to install compatible PTC equipment in their locomotives and submit to corridor traffic control. This would require appropriate clauses in FRA’s aforementioned “rule of special applicability”, consistent with those of the mixed traffic waiver Caltrain has already been granted.

For reference, the in-cab equipment for ETCS level 2 costs less than $0.5 million per unit. CHSRA could easily spring for some number of those so the legacy operators don’t have to. Contrast that with the cost and disruption of needlessly pouring hundreds of millions of dollars’ worth of concrete.

There simply is no operational need for an expensive bi-level design, this is a run-through station with short dwell times even for HSR. The inside platform tracks should be laid out such that Caltrain can reverse direction without crossing the main line. The only other proviso is that an additional yard for mid-day stabling of Caltrain and ACE trains must be secured. I’d recommend looking for that either north of the station (river/Ryland/87/UPRR Milpitas Line, partially above the river) or else at the southern end point of the PCJPB right of way. Please consult the map above for details. The land I have in mind currently belongs to a business called Concrete Ready Mix and is apparently used to store cement, which may or may not be shipped in by UPRR. The property might have to be taken by eminent domain and an existing access road off Hillsdale Ave paved over.

The remaining secondary grade crossings at Auzerais Ave and W Virginia St would be closed, perhaps with ped/bike underpasses. The right of way in the Gardner district would not be widened and no additional grade separation works constructed. There would “only” be additional rail traffic. The curves already there impose a speed limit of around 55mph for acceptble passenger comfort , yet even that may only be feasible with gauntlet tracks to address the superelevation mismatch with UPRR trains. Transparent sound walls plus other noise-reducing measures such as triple glazing should be offered for properties abutting the right of way.

Keep Caltrain/HSR through San Jose as straightforward as possible please, the BART extension to Santa Clara is going to be nose-bleed expensive enough. The city needs to focus on delivering overall public transportation functionality.

Other Retained Stations
SF 22nd St, Santa Clara and Tamien would all be retained as isolated stations on the main line without bypass tracks, which means serving them would reduce line capacity. If and when timetable planners can no longer afford to waste slots on these stations, they will need to be closed or else bypass tracks constructed at that time. In the latter case, dwell times would be on the order of 2.5 minutes for a single overtake scenario.

Impact on Freight Service
Given the 90mph line speed and the need to keep track geometry maintained to a level that is safe even at 125mph, there will be a need for greater superelevation in curves and, for banning super-heavy FRA-compliant locomotives. Perhaps UPRR and its customers could live with restrictions such as night-only operations, an axle load limit of 22.5 metric tonnes and vertical transition gradient of up to, say, 2%. Installing and maintaining a gauntlet track all the way to Santa Clara just for UPRR would not make economic sense and also greatly complicate the design, construction and operations of the aforementioned high-speed turnouts on the main line. It matters little that freight spurs could still be served using the regular kind.

If rail freight business models no longer make sense if restrictions are imposed, PCJPB has the legal right to unilaterally cancel freight service by invoking clause 8.3(c) of its 1991 contract with Southern Pacific. That would, however, trigger federal abandonment proceedings, i.e. compensation claims. Whether there would be the political will to take such action is another matter entirely. Businesses that currently depend on rail freight might well have to relocate or liquidate – at the expense of local jobs – or else, switch to trucking on congested peninsula freeways. CHSRA is still hoping to change UPRR’s mind on ROW acquisition in the Central and Antelope valleys, if not south San Jose to Gilroy, so it’s being cautious. PCJPB might not care as much if it anyhow decided to terminate service south of Tamien.

In addition, planners would also have to weigh the cost of financial compensation against the overall cost savings associated with remodeling the corridor for passenger trains only – free of constraints related to high axle loads, limited transition gradients and access to freight spurs. Also, the small but useful So SF yard would become available for stabling or light maintenance.

Conclusions
Except for the arguably justified extra cost of re-framing the DTX tunnel complex such that it effectively extends out to 22nd St, a lot of cost can be saved by redefining Caltrain service such that it can continue to serve 95% of its current ridership well into the future. There would be some operations constraints on the future HSR operator, including an integrated timetable and limited scope for express trains at certain times of weekdays, but those are a small price to pay at this point considering the HSR starter line is nowhere near fully funded.

Timetable planners would gain a great deal of flexibility in defining 2-3 Caltrain service patterns – albeit based on groups of stations rather than individual ones – while preserving a sufficient number of slots for HSR service. Analysis of current Caltrain ridership between station pairs should guide optimization. Overall, the focus should be on delivering 90+% of the functionality at perhaps 60% of the cost.

For reference, a Firebird could serve the TBT plus 7-8 stations in the peninsula in the same line haul time today’s baby bullets need for 4th & King plus 4-5 stops (albeit different ones). A 16-stop “local” would make the SFTBT-SJ trip in about 70 minutes vs. 90 to 4th & King today. My results are within a few minutes of those returned by the spreadsheet Clem Tillier provided in his post The Tao of Timetables, after plugging in the relevant parameters. However, he did not explicitly take HSR traffic into account.

Recommendations

  • The Firebird concept would reduce the number of miles of new tracks between SF and way point Lick from over 50 to a more manageable 20 or so, while improving service to 95% of Caltrain customers.

    Against that, the concept implies a large number of high-speed turnouts that must be switched frequently and reliably and, the closure of 11 tertiary stations.

    While some difficult section would remain (e.g. Transbay Terminal to 22nd St in San Francisco, Millbrae, San Mateo, Palo Alto), others would be left alone (e.g. 85 to 237 in Mountain View) or “rightsized” (e.g. SJ Diridon station and approaches).

  • Before appropriating any more funds, members of Congress, state lawmakers and peninsula officials should all require CHSRA and Caltrain to deliver an optimized integrated operations plan for the SF peninsula corridor, because that should be driving an integrated capital investment program. This includes important technical details such as electrification design, signaling and traffic management, EMU acceleration performance and platform height harmonization.

    That plan will need to be more detailed and may well be substantially different from the concept described above, which I put together in a matter of days. My point is there are no concrete plans for actually sharing any tracks other than in downtown SF at all right now, because the PRP planners and their consultants are not focused like a laser beam on wringing cost out of the corridor upgrade project. Someone should force them to increase value per taxpayer dollar and ease the environmental impacts.

  • The state of California should ask FRA to urgently station a senior regulator on site in Sacramento, with prop 1A funds used to reimburse it for the additional headcount. This person’s office should be in close proximity to that of his/her counterpart at the California Public Utilities Commission (CPUC), which may also need funds for an additional headcount. Two headcounts is peanuts, absolutely peanuts, compared to potential cost savings related to cutting through red tape as early as possible.
  • Do not actually break ground on the San Bruno project until there is clarity regarding the viability of service there in the context of a Caltrain operations plan for the entire corridor that the peninsula counties are willing to subsidize at the level required. I realize there’s an urgent need for construction jobs and a deadline on the ARRA funds, but that would be a poor excuse for constructing a white elephant.
  • Revisit the design of the 4th & Townsend station, 4th & King yard and the DTX tunnel to eliminate capacity bottlenecks, even if doing so actually increases cost in this section. The long-term success of both Caltrain and HSR operations depends on high throughput at the Transbay Terminal. Planning mistakes made now could come back to haunt both operators and the city decades from now.
  • Give the acquisition of stabling yards for Caltrain/HSR in SF and Caltrain/ACE in San Jose much higher priority.
  • PCJPB should require Caltrain engineering to leverage investments CHSRA will anyhow have to make, especially regarding big-ticket subsystems like electrification and signaling. If need be, CHSRA and PCJPB should transact certain planning prerogatives under the heading of ROW preservation, at a price that will plug the hole in Caltrain’s operating budget for e.g. the next three years. For starters, PCJPB could hand over decision control over the remaining $37 million in prop 1A funds for capital investments in Caltrain, but the counties would still have to reprogram more of their future MTC and other capital investment dollars to the corridor upgrade project. On the plus side, CHSRA could claim those as non-state matching funds in the context of the upcoming request for prop 1A bond appropriations.
  • Strongly consider Mountain View for the mid-peninsula HSR station, since quad tracking between 85 and 237 would be far more expensive than moving the station in the context of a larger remodeling project. Of the three candidates, Mtn View may have the highest ridership potential due to the proximity of 3 major freeways plus Central Expressway, in addition to VTA light rail, buses and bicycle infrastructure.

    A future post will examine the nitty-gritty of the Mountain View-San Antonio section, including especially a concept for managing traffic and connecting transit consequences while upgrading the downtown business district with its popular eateries.

  1. Joe
    Jun 14th, 2010 at 09:52
    #1

    “The last 5 are served by just three trains a day (each way) via trackage rights on UPRR’s central coast line, not because there’s a hard capacity constraint but because there simply aren’t enough potential customers.”

    B.S.

    If Gilroy doesn’t have enough potential customers for Caltrian then it obviously will not have enough potential customers for HSR. I’d be careful with that flippant analysis which would validate the criticism that Gilroy’s 4K ridership predictions are evidence of a bad business plan.

    The problem south of Tamien is **bad** service. I’ve ridden 22nd to PA in the 90′s and now Gilroy to PA.

    Trains are delayed by UP freight and VIP service, the tracks and separation need improvements and frankly the down grade from 4 to 3 trains and spotted service (one of those each way trains doesn’t stop at Palo Alto. So there are effectively 2 trains a day for some stops.

    We use it. We have a monthly pass which isn’t used daily so the body count might not show but we pay the fee.

    If Caltrain wants to cut out Gilroy then I’d prefer south county tax dollars go somewhere else and Love to see the analysis that Gilroy doesn’t have the potential given the in past it has had higher ridership.

    Rafael Reply:

    In the short term, Calrtrain may have no choice but to at least suspend service south of Tamien because the peninsula counties just blew a large hole in its operating budget. If they do, I imagine you’d at least get a refund for the portion you cannot use.

    For reference, Caltrain’s ridership measurements are based on averaging the number of boarding passengers during a particular week in February of each year. The sample size for the weekday number is five, for weekends it’s just two. Inevitably, there are statistical errors, especially for tertiary stations. It’s possible the 119 weekday number for Gilroy isn’t quite representative, but it’s a useful indication compared to total Caltrain ridership of nearly 37000. What is more, the number is consistent with the declining trend since 2001, when it reached a peak of – drum roll please – 569. Basically, ridership in Gilroy has declined ever since 101 was widened.

    The ridership forecasts for HSR include the assumption that folks from Hollister, Watsonville, Monterey and Salinas will all flock to the Gilroy station. Caltrain service on UPRR’s clapped-out track(s) isn’t fast or comfortable enough to generate comparable ridership.

    Afaik, CHSRA plans to run at speeds well above 90mph – more like 150mph+ – between south San Jose and Gilroy. High-acceleration rolling stock suitable for Caltrain operations in the peninsula wouldn’t be able to reach those speeds.

    Elizabeth Reply:

    They plan to run at 220 mph

    Rafael Reply:

    Figures, they need to make up for the time lost between SJ Diridon and Tamien because of the sharp curves in the 280/87 alignment.

    All the more reason to put the Gilroy HSR station, which will receive limited service, east of 101.

    Robert Cruickshank Reply:

    Totally agreed.

    I cannot express this strongly enough: I do not at all agree with Rafael’s proposal to close down stations.

    Rafael Reply:

    Unfortunately, Caltrain has declared a “fiscal emergency” for the second year running and there is no initiative on the 2010 ballots of the peninsula counties to plug the hole in its operations budget via sales tax hikes. Therefore, the railway has no choice but to cut service anyhow, at least for now. Service to Gilroy is likely to be near the top of the list of candidates.

    http://www.mv-voice.com/news/show_story.php?id=2943

    Eliminating tertiary station does leave some passengers in the lurch, but unless someone writes Caltrain a large check, that’s where this is headed. Does it make sense to burden the entire corridor upgrade with many hundreds of millions of additional cost while delivering reduced operating flexibility, just so Caltrain can keep serving e.g. 59 weekday riders at College Park or even 387 in Belmont?

    political_incorrectness Reply:

    If stations do not have any suitable TODs that can generate ridership and there is a fiscal emergency, it is time to make efficencies in spending and cut down as much as possible without impacting the 95% of customers. I would hate to see the Gillroy section go since that would put a dent in plans for Monterrey extension. However, there would need to be more reliable service such as dual track 90 mph. Low ridership stations need to be suspended at this point in time due to fiscal emergency. If you want to bring back the stations, entice developers to develop near them.

    Rafael Reply:

    “If you want to bring back the stations, entice developers to develop near them.”

    Or perhaps, TOD should be encouraged near stations that will definitely be served anyhow.

    As for the Monterey extension, which presumably refers to TAMC’s ambitions to extend Caltrain service to Salinas, it might make sense to extend Amtrak’s Capitol Corridor instead. That service will continue to own and operate FRA-compliant diesel equipment, whereas Caltrain will migrate to a fleet of electric EMUs. However, none of the counties that would be served wants to pay for dual tracking at 90mph and maintain that for a handful of trains per day.

    Robert Cruickshank Reply:

    The Caltrain extension is on the back burner at best. TAMC is currently focusing on the Capitol Corridor as a way to bring rail to Salinas.

    Rafael Reply:

    That makes a lot of sense to me, though Placer county will be first in line for an extension. If the Gilroy HSR station ends up east of 101, near the premium outlets mall, it would make sense to construct a new standard speedd spur off the UPRR line approaching from the south-west around the eastern end of town to facilitate transfers. At that time, TAMC could operate its own regional trains between Salinas, Watsonville and Gilroy HSR only – a true HSR feeder operation. Such a spur would carve up some farmland, which should be reserved as soon as CHSRA makes its siting decision. There would also be a need for (a) platform(s) and possibly a tail track for stabling.

    Passengers destined for downtown Gilroy would transfer to the bus VTA will no doubt be asked to operate for the locals. San Benito county might operate a separate one between Hollister, downtown Gilroy and the HSR station.

    joe Reply:

    “If you want to bring back the stations, entice developers to develop near them.”

    Has anyone seen how much $$$ Gilroy has pumped into the Downtown Caltrain station and areas nearby including high density live work lofts?

    o The city redeveloped downtown Monterey Ave from 8th to 4th.
    o Approved new, high density homes on the near east side, Cannery District (Forest Park and Alexander Place (39 and 32 Homes respectively).
    o There are several new 3 story live work lofts from 3rd to 5th street.

    The city has been a poster child of building up and supporting a walkable downtown so the idea we need more development nearby to earn a Caltrain stop is laughable to me if it were not so wrong. It’s a talking point with no grounding in fact.

    The argument to maintain frequent, convenient service up for SOME riders invalidates the claim South County isn’t dense or interested in Caltrain.

    Lose South County Santa Clara and you’ll lose county support for Caltrain form PA downward.

    This proposal to cut stations is a death spiral.

    Leave out cities and they’ll return the favor – they’ll stop backing Caltrain.

    Rafael Reply:

    I understand the argument, but Caltrain is facing a death spiral even though it’s providing service to such a large number of stations.

    Wrt Gilroy, I’d say this: if CHSRA cannot secure full funding for SF-SJ, there’s no chance it’ll secure full funding for SJ-Merced/Fresno. And with costs high and escalating, it’s getting more not less difficult to secure full funding of the tail sections. Therefore, if Gilroy residents want an HSR station they should focus on keeping Caltrain alive because if it dies, BART will be called in to pick up the pieces. At that point, HSR would become more expensive to implement because the two services run on incompatible gauges, so quad tracking all the way would be the only option. BART also has long-standing policies regarding station layouts, parking lots etc. The expense of all of that could easily lead to HSR getting severely delayed or canceled.

    Therefore, the objective has to be keeping Caltrain alive with a plan to improve its prospects for long-term viability. If that entails closing tertiary stations, so be it. Ultimately, HSR service between Gilroy and the peninsula will be far superior to anything Caltrain could ever hope to achieve on UPRR’s tracks.

    joe Reply:

    ” I’d say this: if CHSRA cannot secure full funding for SF-SJ, there’s no chance it’ll secure full funding for SJ-Merced/Fresno.”

    HSR is the entire project , not pieces and segments. Prop was clear.

    When it looks like it’s prioritized for urban hipsters then HSR is dead. We hang together or hand separately.

    “Therefore, if Gilroy residents want an HSR station they should focus on keeping Caltrain alive because if it dies, BART will be called in to pick up the pieces.”

    Gilroy residents do want to keep Caltrain alive, sadly that puts us in conflict with your awesome plan.

    Caltrain electrification always bugged me because I saw it as a consolidation and threat to Gilroy service. It is. Great. Nice way to build trust. Consolidate service but tax the larger community. We get to ride express buses. Well that lame solution goes for the entire Caltrain line – all of which is subsidized.

    Also, you are validating some very bad talking points such as the lack of interest in train service in south county and blaming the cities i.e. needing more city development around the train stations. Totally false in Gilroy’s case. We’re building new and up and it’s a walkable downtown.

    The problem is 1) 3 trains only one way AM and PM 2) very limited service north, 3) crummy service and ROW south of Tamien 4) and a recession that has hurt jobs and cut ridership 5) parochialism.

    Caelestor Reply:

    Is it possible to shut down some of the stations south of Tamien, but not all of them? Feeder buses could be a possible solution.

    Another possibility would be to replace Caltrain with the Capitol Corridor and have a cross-platform transfer at Diridon (someone’s going to criticize me on this).

    Still, I’m surprised a town that barely uses the train actually wants to preserve it. There clearly is an appreciation for public transport in this country!

    rafael Reply:

    Considering TAMC will now be asking the CCPJA rather than Caltrain to provide service to Salinas, I expect that some level of diesel-based passenger rail service to Gilroy itself will be maintained or interrupted only briefly. Morgan Hill is another matter.

    Regarding the impact of the recession on Caltrain ridership in Gilroy, here are the average weekday ridership numbers since 1992. Evidently, risdership grew between 1992 and 2001 and then started to decline. You cannot blame the current recession for all or even most of that. Instead, blame the lanes that were added to 101.

    1992 – 112
    1995 – 198
    1996 – 182
    1997 – 300
    1998 – 394
    1999 – 420
    2000 – 468
    2001 – 569
    2002 – 421
    2003 – 357
    2004 – 226
    2005 – 210
    2006 – 141
    2007 – 144
    2008 – 149
    2009 – 158
    2010 – 119

    Source: http://www.caltrain.com/ridership_info.html

    Caelestor Reply:

    South of Tamien is a lost cause after the freeway widening. Express buses could do a much better job.

    The other stations, however, should be examined in their individual context. How many passengers per train that stops there? Only one train stops at College Park to serve Bellarmine High School, so I see no reason to eliminate the station.

    Another factor is distance. Removing Bayshore leaves a gap in areas serviced, so I would not recommend that. Hayward Park, however, has two major stations to its north and south.

    Caelestor Reply:

    P.S. There’s 10 stations you’d eliminate, not 11.

    Rafael Reply:

    Good catch, I forgot to list South SF. It is actually 11. Fixed, thx.

    Rafael Reply:

    There’s certainly scope for discussion about service levels at the stations I recommended be closed. The infrastructure is already there, if there’s a free slot in the timetable it may be possible to offer very limited service such as 1 train per day each way.

    Regarding Bayshore, I don’t buy the argument that there would be too large a gap in the service area. However, since the station is quad tracked, it may be possible to offer limited service if the anaemic ridership is concentrated on just one or two trains per day.

    However, I do think timetable planners will have to make some hard-nosed choices as a significant number of slots on the timetable will actually be needed for HSR service. Using a 2 minute headway creates more slots to play with, but express HSR trains will each consume several.

    joe Reply:

    Buses suck. I’ve ridden express buses and they are road bound and undependable.

    But please people, what makes the entire Caltrian service immune to the argument to use Express Buses? Turn 4th and King into a Bus terminal.

    Express Buses run from Stanford up El Camino to SF. People ride these express Buses all the time.

    Rafael Reply:

    Buses don’t provide the capacity a rail line does, they’re slower and in many cases, actually more expensive to operate. However, it’s possible that some motorcoaches will be used to provide limited substitute/supplemental service during the construction period.

    Note that the Transbay Terminal is a bus terminal. Evidently, many people prefer to travel by train when given a choice.

  2. synonymouse
    Jun 14th, 2010 at 10:01
    #2

    BART is a simpler and more familiar solution and already has a bureaucracy in place that can implement it.

    Rafael Reply:

    And BART cannot accommodate any express service at all. It’s a locals-only urban subway with miles that are 50+ miles long, not a rational regional service. Besides, it runs on broad gauge tracks which are completely incompatible with HSR.

    You’ve obviously missed the entire point of this post, which is expanding capacity to mix different stop patterns, including non-stop HSR express trains. Either that, or you’re being wilfully obtuse.

    Evan Reply:

    I think he was joking. I hope.

    Peter Reply:

    No, he wasn’t joking. He’s simply a troll.

  3. adirondacker12800
    Jun 14th, 2010 at 12:27
    #3

    Train designs for top speeds of 125mph necessarily feature longer transmission gear ratios and hence, lower acceleration performance at low speeds.

    That may have been true in 1950. Nowadays the ‘lectric trains have sophisticated power supplies that shape the voltage and frequency depending on the task.

    In Palo Alto, the layout of the Univ. Ave/Alma St grade separation intrudes on the railroad right of way.

    The one over University Ave itself? If I remember correctly that one is already four tracks wide and has been since the upgrade in 1940.

    At San Antonio Rd, ramps to Central Expressway and the Caltrain platforms mean the available ROW is too narrow for quad tracking.

    Move the Caltrain platforms. Looks like they had that in mind when the built the pedestrian underpass in at the south end.

    Note that 4th & Townsend would nominally be a Caltrain station paid for by CHSRA under the heading of ROW acquisition, subject to an easement that would let the future HSR operator leverage the platforms for a nominal fee. This is legalese sophistry but it just might get CHSRA out from under the 24 station limit in AB3034. The same – admittedly tortured – logic could perhaps apply to the mid-peninsula station.

    Pick the same platform height etc and any Caltrain station is an HSR station.

    for banning super-heavy FRA-compliant locomotives.

    Super heavy FRA compliant locomotives travel over class 6 track all the time.

    Rafael Reply:

    a) I wasn’t talking about speed control via power electronics. Without those, variable speed operation wouldn’t be possible at all. I was talking about the fixed ratio of the final reduction gears. With the same electric motor, you can trade off traction force at the wheel against feasible top speed.

    b) The Univ. Ave underpass in Palo Alto as such is indeed wide enough for four tracks and would not need to be demolished. It’s just that some of that width is used for roads on both sides, with Alma St. being the one that is forcing a chicane on the rail alignment. That street will need to be kicked off the structure – which is PCJPB property – so the main line can be straight enough for operation at 125mph. The other road is used for vehicular access to the station.

    http://maps.google.com/maps?f=q&source=s_q&hl=en&geocode=&q=palo+alto&sll=37.0625,-95.677068&sspn=43.037246,74.003906&ie=UTF8&hq=&hnear=Palo+Alto,+Santa+Clara,+California&ll=37.443107,-122.164316&spn=0.001322,0.002258&t=h&z=19

    There’s not enough money to put four tracks underground and doing it for just the main line would still prevent Caltrain from doubling service frequency, as it believes it needs to do.

    c) The San Antonio station could be moved away from the overpass to where there is more lateral room for platforms, but quad tracks would still have to run through. The constraint is that the ramps do not offer enough vertical clearance for a train + OCS. Lowering the rail alignment into a shallow trench might work, but it would probably be cheaper to remodel the overpass. Per Clem, it’s not up to seismic code anyhow.

    d) Platform harmonization should absolutely be a design goal, especially for the nose-bleed expensive Transbay Terminal up in SF. The vexed issue is if HSR should harmonize down to the 550mm or so that Caltrain would like or else, if Caltrain should harmonize up to the 1000mm+ that CHSRA would prefer. Right now, the two have not reached agreement and are proceeding on the assumption that platforms will not be harmonized.

    e) A 125mph, the track geometry tolerances are not as tight as they are at 220mph. Nevertheless, heavy locomotives do increase maintenance overheads for regular ballast track. Slab track with a solid foundation is a different matter, as is ballast track with extremely stiff extra-heavy rails like those laid down by the old Pennsylvania railroad.

    Still, there are also other reasons why maintaining existing freight service levels on the SF peninsula may not be cost-effective in the context of the corridor upgrade. Unlike the majority of tracks in the US, this is already primarily a passenger corridor.

  4. synonymouse
    Jun 14th, 2010 at 12:32
    #4

    Not joking in the slightest. BART is a proven system with deep resources. BART’s higher frequency of service, plus seamless extension of existing or under construction lines make it comparable or superior to express Caltrain, especially off-peak and weekends.

    The mostly 2-track express idea is a “just in time” tweak that would be every as susceptible to ripple service delays as BART due to equipment failure or accidents.

    Rafael Reply:

    BART’s funding is more secure because that organization enjoys funding primacy at the transportation authorities of member counties. Caltrain does not enjoy similar privileges at SF Muni, SMCTA and VTA.

    The BART extensions are actually a huge problem for the operations department. That’s why they insisted that the one to Antioch be implemented as a separate service with a transfer station.

    BART’s average speed is lower than that of Caltrain’s baby bullets. It would be much lower with Firebird service.

    As for service frequency, it depends on the station you’re at. Baby bullet stations get a train every 15 minutes or so during rush hour. More frequent service requires either lighter rolling stock (exactly what Caltrain now has permission to pursue) operating as locals or, additional quad track sections. Either way, full grade separation is needed for safety and cross road capacity. BART has always had that because third rail electrification requires it for safety.

    The main line + sidings concept is common elsewhere in the world, though it is usually used for lower line speeds. It’s not a tweak and, there are ways to include sufficient reserves in the design to make it robust against common issues such as a passenger who delays departure by a few seconds. Breakdown risk would be managed via proper maintenance. Accidents are extremely rare on fully grade separated lines with positive train control.

    adirondacker12800 Reply:

    Breakdown risk would be managed via proper maintenance.

    Murphy was an optimist.

    wu ming Reply:

    USE THE REPLY BUTTON

  5. David S
    Jun 14th, 2010 at 14:08
    #5

    Robert & Rafael:

    Even if we disagree about the specifics of such a plan, I think the call for a truly integrated plan is completely justified. A lot of people watching this project do see the possibility for a hundreds of millions in essentially waisted dollars if not executed in the best possible (with emphasis on the word possible) manner.

    1) HSR needs to happen for the state
    2) The peninsula cannot be left without commuter rail
    3) For 1 & 2 to happen, an integrated plan seems necessary.

    How do you two suggest we help convince our representatives and the respective transit boards of these facts?

    Rafael Reply:

    I’m not really a political activist, so I’m a little stumped on that one. I figured it would make sense to put forward a fairly concrete concept to get informal discussion going first. There will be some who accept the argument that 95% service is better than the risk of none at all.

    Others, such as Robert, remain unconvinced that Caltrain’s fiscal emergency cannot be overcome in ways that don’t involve any permanent cuts in service. Any time transit advocates accept service cuts, there’s a risk they’ll get nothing in return. Politicians like to take credit for building things. Finding funds for operating subsidies is yeoman’s work, at least until a service becomes so popular that cuts have consequences at the ballot box. It’s entirely possible that the threat to shutter Caltrain in 2012 is no more than saber-rattling in the hope of provoking a public outcry from passenger representatives.

    The folks at CHSRA have indicated to Robert and I that they do monitor this blog, perhaps someone at Caltrain or PCJPB will read this post as well. My guess is quite a few Caltrain customers do as well. Let’s give them a couple of days to digest this, it is after all possible someone will point out a serious flaw in my thinking.

    As for convincing representatives, I’m not looking for those in charge to support this exact plan. Simply getting them to agree that capital investment planning should be based on a viable concept for future operations would be a good step forward at this point. The focus ought to be on maximizing long-term transportation value, but right now there’s a scramble to create construction jobs using ARRA funding for projects with completed – if imperfect – environmental review documents.

    For starters, the list should include the PCJPB and Caltrain’s board of Directors plus the body AB3034 set up to provide oversight of CHSRA.

  6. Adam
    Jun 14th, 2010 at 14:52
    #6

    I like the idea, but even more I like that someone is thinking a little outside the box. Building the additional rails in this manner obviously allows full 4 tracking to be done in the future if ridership ever requires it.

    Rafael Reply:

    Yes, sidings could be modified and new ones added in the future to capture additional ridership. However, the initial focus should be on growing ridership beyond current levels at the stations that are already busy, because only then can operating subsidies per passenger come down to levels that enjoy sufficiently broad political support. Caltrain needs a solid financial foundation before it can reverse the service cuts it is already being forced to make.

    It’s a difficult argument to make initially, because any cities that see their service cut will also lose interest in paying for service to other cities. Fortunately, Caltrain is funded at the county level.

    On the plus side, even the initial Firebird service would help make HSR actually happen, which everyone would benefit from.

    adirondacker12800 Reply:

    It will be very very expensive to do that while maintaining service on a busy railroad…. and the railroad will be busy or otherwise they wouldn’t be adding track. And they’ll have to maintain service because it’s a busy railroad.

    rafael Reply:

    Yes, the plan is to maintain Caltrain service during the corridor remodeling project, on a modified schedule. It does make everything take longer and cost more, but unless Caltrain and UPRR service are both shuttered for a couple of years, there’s no way to substantially speed up the construction of grade separation work, to reduce ROW width needed during construction and, to reduce construction cost.

    You’d need a large fleet of buses and temporary bus-cum-construction-traffic lanes on roads such as El Camino Real to provide substitute service if you’re going to shutter Caltrain for more than a few days. Ridership will take longer to bounce back, because it’s famously difficult to coax drivers out of their cars.

    Shuttering UPRR would, of course, be whole other ball of wax.

  7. Jon
    Jun 14th, 2010 at 15:56
    #7

    Wouldn’t it be preferable to navigate the DTX loop in a clockwise rather than counter-clockwise direction, to facilitate a possible future extension to the East Bay in a new Transbay Tube?

    Jon Reply:

    I guess that would mean adding an extra vertical layer as the tracks cross over, or complicating the signalling. Nevermind.

    Rafael Reply:

    In the US, trains run on the right. The loop direction shown avoids the need for crossing the tracks.

    If there is a desire to build a standard-gauge transbay tunnel, that could farily easily connect at Embarcadero/Main. An additional turnout at 3rd/Townsend would permit trains headed to the TBT to return to the East Bay. Through trains would also be possible, though eastbound ones would need to traverse the section between 3rd and Main twice, creating a capacity bottleneck. Therefore, such trains would probably stop at 4th & Townsend instead.

    To compare that with the ease of extending the tracks to the water’s edge under TJPA’s terminal plan, consider that CHSRA requested that the east ends of all platforms be moved all the way to the east side of Main St. to ease the throat curvature and improve throughput. It would also put passengers closer to Embarcadero BART and the ferry terminal but further from the transbay buses.

    TJPA has decided to map that into an unfunded future phase 2 modification because it has a Decision of Record plus $400m in ARRA funds for its own design, which calls for platforms to terminate at the west end of Beale St. to avoid near-term impacts on this skyscraper.

    A future extension to the water’s edge and across to the east bay would have to tunnel under at least one additional block of skyscraper to reach Howard St and then and also dive under the SF Muni tracks that begin their descent south of Howard/Embarcadero. In other words, it would be very expensive to ever upgrade TJPA’s flawed tunnel design to run-through tracks and then only for trains headed to the East Bay.

    A single track loop via Main and 3rd would be much more elegant, but the decision to build the train box now because ARRA funds happen to be available will actually lock SF, HSR and Caltrain into a suboptimal terminal station concept for decades. TJPA is already planning for a phase 2 to at least mitigate the planning mistakes it has set in stone for phase 1.

    To be fair, part of that is CHSRA’s fault. TJPA did offer a loop tunnel via Main and 2nd, which Caltrain of course loved to death. However, it did not offer dead-straight full-length platforms and CHSRA was apparently too hung up about its 30-40min dwell time requirement for train cleaning to fight for moving the outbound tunnel to 3rd. Cleanliness is next Godliness, indeed.

    Jon Reply:

    Thanks for the detailed information.

    adirondacker12800 Reply:

    will actually lock SF, HSR and Caltrain into a suboptimal terminal station concept for decades.

    For centuries if not forever.

    rafael Reply:

    Maybe. London and Paris still operate multiple 19th century terminal stations. TJPA’s decision against building a run-through station is a mistake that isn’t even built to last yet.

  8. Alon Levy
    Jun 14th, 2010 at 17:20
    #8

    Rafael, I still don’t see the benefit this plan has over a version of the existing plan without the more difficult grade separations. The amount of widening that is needed in the existing plan is small, and most of the cost of rail is not laying the tracks but grading the right of way.

    Rafael Reply:

    CHSRA’s plan calls for dedicated HSR tracks and converting Caltrain to slow local-only service. Mine would give Caltrain the option to operate one or more limited/express services to serve all of the stations during rush hour. These could easily be adapted to evolving commute patterns over time. Caltrain depends on non-local trains for a large fraction of its ridership, so growing that will depend on speeding up commutes and/or increasing train frequency. Preferably both.

    Also, my concept would reduce the total distance that needs to be quad tracked from 50 miles to around 20, since one siding would leverage existing quad track. Sure, fully grade separating the other 30 miles would still cost serious money, but substantially less for two tracks than for four. Many crossings are already separated for two tracks and could be left alone. At others, a road under- or overpass may be acceptable for two tracks but not for four, due to impacts on connections with frontage roads like Alma/Central.

    Big gains would come from not having to construct anything new at all in certain difficult but already fully grade-separated sections, e.g. 85 to 237 in Mtn View, the So SF yard, Bayshore to 22nd St in SF and Santa Clara to the Monterey Highway. It would also avoid blowing $300m on a new station in San Bruno.

    Alon Levy Reply:

    Is SSFF a foregone conclusion? I know they’re biased toward it right now, but my impression was that SFFS and FSSF were still on the table, at least officially.

    In either case, if you’re looking for alternatives to SSFF, then FSSF is a much more straightforward one than what you’re proposing.

    Caelestor Reply:

    The problem is the politicians are apparently blind and/or deaf.

    rafael Reply:

    Planners could choose either SFFS or FSSF track order, but on a siding-by-siding basis rather than individually for each station.

    The Firebird concept is essentially incompatible with to SSFF or FFSS, because that would generate interference between northbound and southbound traffic. That would be exactly what you don’t want on a 90mph high-throughput main line shared by Caltrain and HSR.

    adirondacker12800 Reply:

    That’s what railroads do now instead of calling the extraordinarily long siding a siding they call it the local track.

    rafael Reply:

    A rose by any other name.

    Alon Levy Reply:

    It’s a bad idea to pick different orders for different sidings, because it makes it impossible to join the sidings together later, if more capacity is required.

  9. Tony D.
    Jun 14th, 2010 at 19:39
    #9

    Hypothetically, if BART were running from SJ to Morgan Hill/Gilroy the trains would be PACKED! Why? Simple: frequent, grade-separated, evening/weekend service, and modern compared to the current Caltrain service to Gilroy, which is not frequent, not grade-separated, no evening/weekend service and operating crummy diesel locomotives. So to say that low Caltrain ridership to Gilroy would equate to low HSR ridership is absurd! Give us “BART on steriods” and commuters will bail on 101! Throw in the Central Coast crowd to a Gilroy station and it’s all good for HSR.

    Tony D. Reply:

    By the way Rafael, that was one hell of a post! Great Job!

    rafael Reply:

    Extending BART to Gilroy? Fuggedaboudit, there’s zero ROW and no viable business case for that. Even the extension to Santa Clara will have to be exempted from normal FTA cost-benefit calculations, not because of ridership but because tunneling under San Jose is so nose-bleed expensive.

    Besides, now that the extra lanes on 101 down to Gilroy have been built and HSR is being built, there’s really no point in spending a boatload of money to make sure they’re not used.

  10. Clem
    Jun 14th, 2010 at 20:41
    #10

    Sure would be interesting to see a recovery from this, fresh from this evening’s commute. Or a shopping cart on the tracks near Anaheim. (Oh, right, grade-separated with intrusion detection… let’s say a suicide off a platform in Mountain View, or an intrusion false alarm near Anaheim)

    The downfall of an intensive overtake scheme is that unless you nail every single one perfectly, at the right place and the right time, when reality strikes the whole timetable falls apart like cascading dominoes. Overtakes are useful and absolutely critical to tap into the potential capacity of a transportation corridor, but they must be judiciously placed and minimized if at all possible. And even then one must plan for them to fail on occasion.

    There’s a much wider issue which goes to answering many peninsula residents’ legitimate question: “what’s in it for me”. One of the selling points of electrification is that it can restore the local commuter service that was already cut when the Baby Bullet was instated. With four tracks that selling point becomes vastly improved commuter service that not only restores local commuter service but expands it and speeds it up. If there is no local trickle-down from the HSR project on the peninsula, and if you can’t offer something better that wouldn’t remotely have been possible in a two-track-only electrified Caltrain scenario, then you’re showing up with empty hands.

    Caltrain Icarus?

    rafael Reply:

    It’s true that I haven’t done any analysis of robustness in off-design conditions, except to note that there is spare acceleration potential in the section between the stations on the sidings.

    Wrt suicides off platforms, those are actually a problem for the Japanese shinkansen system. In that country, the grieving relatives receive a stiff for the disruption their not-so-dearly departed caused. That’s harsh, but it’s what they do to keep trains running on time down to the second.

    Also, wouldn’t the officially planned system also be susceptible to accidents/suicides at platforms and false alarms from the intrusion detection system? And wouldn’t both services be affected anyhow, since they’re sharing the DTX tunnel in SF? Seems to me you’re setting up a bit of a strawman argument there.

    adirondacker12800 Reply:

    With a four track railroad they can announce “There is police activity at Atherton, we won’t be stopping at Atherton and will be delayed because we have to go slowly through that area on the express tracks.” With a two track system they announce “There is police activity at Atherton on our track, as soon as the buses get here we will be shuttling you into San Francisco”

    rafael Reply:

    Excuse, but what police activity would there be on the tracks? They’ll be grade separated and fenced off.

    If you’re referring to a (suspected) act of sabotage or terrorism, you can be pretty sure the police would temporarily shut down all tracks in the area anyhow. It’s yet another strawman.

    adirondacker12800 Reply:

    Some idiot drops his iPhone on the tracks and decides to jump down. It rains hard and the tracks short out making the signals think the track is occupied. Some decides to have a medical emergency the train stops at the station until the ambulance arrives. MUNI is on strike so three times as many people as usual bring their bikes along. It’s windy and debris blows onto the tracks. Running to shcedule works out real well in Microsoft Train Simulator, not so well when it comes to real tracks, real passenger and the rest of real universe.

    Peter Reply:

    “Some decides to have a medical emergency the train stops at the station until the ambulance arrives.”

    I can definitely relate to that. My wife and i nearly missed our train to Prague because of a medical emergency on the S-Bahn in Berlin at Zoologischer Garten. That was the first time I had ever seen them have to do unplanned single-track in Berlin, and I lived there for 13 years…

    rafael Reply:

    “Some idiot drops his iPhone on the tracks and decides to jump down.”

    He’d have to cut through the fences first. Yes, fences on overpasses.

    “It rains hard and the tracks short out making the signals think the track is occupied.”

    Get a signaling system that wasn’t designed by British Rail.

    “Some decides to have a medical emergency the train stops at the station until the ambulance arrives.”

    Yes, that can happen once in a blue moon. So can earthquakes and other freak events.

    “MUNI is on strike so three times as many people as usual bring their bikes along.”

    That doesn’t mean they’ll all be allowed to bring them onto the trains.

    “It’s windy and debris blows onto the tracks.”

    And it wouldn’t blow onto the tracks if there were four all the way instead of just two in some places?

    Frankly, any and all of these scenarios could apply to an implementation featuring four tracks all the way as well. Yes, more trains and therefore, more passengers would be impacted in any scenario that involves track sharing. The official plan is to share track in downtown SF only, my concept would merely expand that to track elsewhere in the peninsula.

    Yes, recovering from an incident is harder when the timetable is busier. That’s why timetable planners get paid big bucks to include sufficient padding and, operators and others have to have emergency response plans.

    Peter Reply:

    I think adirondacker was talking about idiots dropping their phone off of the platform. Happened just recently on BART if I recall correctly. I think the guy had trouble getting back up, with a train oncoming.

    adirondacker12800 Reply:

    Happened recently on the New York City subway, she wasn’t so lucky. Fouled up service for hours while they removed the body parts.

    Peter Reply:

    Darwin Awards candidate right there.

    rafael Reply:

    Darwin award!

  11. synonymouse
    Jun 14th, 2010 at 21:07
    #11

    Mega=Meg may be the Governator in drag but she has a 50-50 chance, lives in Atherton and by the look of things has a temper. If I were the honchos in the hsr-Caltrain fuhrerbunker I would start working at total compatibility ’cause some heads could roll come January.

    rafael Reply:

    IIRC, the Governor only appoints some – not all – members of the CHSRA board. In principle, board members are appointed for four-year terms.

    synonymouse Reply:

    The Governor is in a position to put all sorts of pressure on the CHSRA. This is not obvious now as Schwarzenegger is compliant and supportive.

    A disgruntled Whitman could call for a modification-replacement of Prop 1A to be placed on the ballot.

    rafael Reply:

    Getting an initiative onto the ballot requires either a 2/3 majority in both houses of the state legislature or an expensive signature drive. Whitman could easily afford the latter and fund a campaign to get HSR quashed, regardless of whether or not she wins the election. So far at least, she’s not seen red on the HSR concept as such, though I’m sure both candidates will promise to get tough on oversight of CHSRA etc.

    My guess is the more divisive issue by far will be the $11b water bond. Whisky’s for drinking, water is for fighting over.

    synonymouse Reply:

    The discontent I am referring would be an amalgam of all the problems and shortcomings associated with the current plan, including funding. And there is the outside chance that the divisions of opinion over the hsr may become such that that real options could have to be presented to the public, especially if the whole project stalls. It would be interesting to speculate if the new CEO is sold on the current scheme.

    For me the water bond issue is a no-brainer – a naked LA power play just like the Palmdale- Tehachapis caper. Once burned, forever learned.

    Peter Reply:

    Given that he’s stated he’s not going to start from scratch, I think he’s ok with the current plan. Tough luck.

    rafael Reply:

    Btw, Meg Whitman is a woman.

  12. John Burrows
    Jun 15th, 2010 at 00:29
    #12

    Closing down more caltrain stations—I hope not—But if it somehow became part of a make or break situation upon which the survival of HSR depended, then ???????

    In regard to Diridon Station: Diridon has 5 tracks plus 2 for VTA. The construction I see going on right now, from what I’ve read, will add 2 more tracks plus required platforms for a total of 7. You mention that 6 tracks at Diridon will be enough for everything (excloding VTA), so I guess that 7 tracks will be even better. The cost of this project is around 50 million. How does this tie in with your Firebird plan? I assume that 4 of the 7 tracks will need lengthened loading platforms to accommodate HSR.

    The preliminary CAHSR concept for an elevated Diridon Station shows the nearest track about 150 feet from our front door and at an elevation higher than our rooftop. A single level station would be great for me personally. At least we wouldn’t be looking up at every bullet train that came through.

    rafael Reply:

    See my reply to Yes on HSR here.

  13. dejv
    Jun 15th, 2010 at 04:46
    #13

    Train designs for top speeds of 125mph necessarily feature longer transmission gear ratios and hence, lower acceleration performance at low speeds.

    Is 1.62 m/s^2 of SF 5000 family too low for your concept?

    Alon Levy Reply:

    I don’t see acceleration rates in your PDF.

    rafael Reply:

    Of course not, acceleration data only make sense for whole vehicles, not individual bogies. Besides, there’s a big difference between acceleration at standstill and average acceleration from 0 to 90mph.

    Finally, high acceleration and deceleration rates impair passenger comfort to some extent, which is bad for ridership.

    dejv Reply:

    The Flirt you used as a base of your calculations has two of five powered bogies with total 2600 kW of hourly output. Five SF 5000 bogies can provide total 2500 kW of continuous power output, so a vehicle with similar layout as DB classes of 422 or can have the same acceleration rates with top speed of 200 km/h. The S-Bahn vehicles are usually limited to 140-160 km/h is because it’s impractical to run them faster, not because of technical limits.

    rafael Reply:

    True, but beside the point. The FLIRT has a rated top speed of 160km/h, I’m suggesting a line speed of 144km/h for operational reasons. You’d need excessively long acceleration sections to support a line speed of 200km/h in the peninsula.

    Besides, electricity isn’t free even if there’s enough traffic to permit some recycling via recuperative braking. In other words, you want a vehicle that has the required passenger capacity plus acceleration performance but is otherwise as light as possible.

    dejv Reply:

    I questioned your point that top speed was limited because higher top speed would impair acceleration. IFF such vehicle made operational and economic sense*, the manufacturers could produce it with existing traction equipment & bogies, so the development is limited to pretty cheap and straightforward carbody design.

    * for example: Baby Bullets on fast tracks of quad-tracked Peninsula line continuing south to Gilroy on CHSRA’s line with Caltrain-only station in Morgan Hill

    adirondacker12800 Reply:

    If they pick the same platform height etc, any Caltrain station can be an HSR station and vice versa.

    Rafael Reply:

    Platform height, distance to the tracks, length and curvature all factor into that. More importantly, though, HSR service depends on stopping infrequently and on not blocking the main line. Timetable have to be both integrated and robust to permit sharing not just a main line but also platforms at selected stations. Doable, but not trivial.

    I was referring to the legal issue of the 24 station limit in AB3034. If PCJPB insists on a cash payment for its ROW in return for easements that permit the HSR operator to use selected Caltrain stations for a nominal fee, CHSRA could perhaps work around that limit at zero additional cost.

    dejv Reply:

    Minimum acceleration for vehicle with 100 % axles powered is maximum tractive effort per axle divided by maximum axle load. Real vehicles are lighter, so some trucks are unpowered to further reduce weight.

  14. Peter
    Jun 15th, 2010 at 10:44
    #14

    http://www.cahighspeedrail.ca.gov/library.asp?p=13740

    WTF is up with the latin words?

    adirondacker12800 Reply:

    They are making sure the three people in Bakersfield that are moderately fluent in Latin have something on the site to consult. . . they’ve read all the whining here about how nobody told anybody nuttin’ about nuttin’

    Paul Dyson Reply:

    Totum scrotum est.

    PD

    adirondacker12800 Reply:

    Ecca! quoque magnae
    Was the play on tree seeds deliberate or am I reading too much into this?

  15. HSRforCali
    Jun 15th, 2010 at 13:02
    #15

    Rafael, is it possible to place the HSR platforms at-grade in San Jose Diridon? If so, couldn’t you use the existing Caltrain tracks to Tamien?

    rafael Reply:

    It’s non-trivial because there will be six separate railways (Caltrain, UPRR, Amtrak Capitol Corridor, ACE, Coast Starlight + HSR) that will need to run trains between Santa Clara and San Jose and 4-5 of those will need to do so south of the station.

    Caltrain and ACE currently use some space at the station for mid-day stabling.

    The presence of VTA light rail is inconvenient, especially in the narrow section between Park Ave and W San Carlos that cannot easily be widened to the east due to a high tension power line and associated pylons.

    Complicating matters are things like incompatible platform heights.

    The biggest issue, though, would be securing FRA approval for mixed traffic in the Santa Clara-Monterey Highway stretch. UPRR in particular won’t be happy with that at all.

    All of that said, I do believe it should be possible to provide sufficient capacity for all concerned in a well-designed single-level station. There’s only so much lateral room, though, and with the ballpark coming, not much scope for widening at the station proper. You don’t want more platforms than necessary, because the ones you do build need to be wide enough to cope with pedestrian traffic volume, e.g. on days when there are ball games.

    HSRforCali Reply:

    So even if HSR only shared the existing tracks only north of Tamien, it’d still be a bad idea even though they’d be going the same speed as regular service? Since the Authority is now studying a shared-track alignment between Anaheim and Los Angeles, couldn’t the same thing be done between Tamien and San Jose Diridon?

    rafael Reply:

    Yes, that’s what I had in mind: HSR, Caltrain, UPRR, Amtrak Coast Starlight, Amtrak CC and ACE all sharing some or all of the already existing tracks between Santa Clara and way point Lick near the Monterey Highway, via a “rule of special applicability” from FRA. CHSRA needs one of those anyhow, for its entire network. In this stretch, the one and only positive train control and traffic management system would be the one CHSRA picks for its network and everyone else would leverage that.

    The curves through the Gardner district are fairly tight, figure 55mph max. if there’s sufficient superelevation (via Gauntlet tracks if need be). The “iconic” bridge across 280 and 87 plus elevated approaches would be massively more expensive and feature even tighter curve radii. Any faster than 50mph and passengers would lose their lunch.

    Btw, it’s possible to run trains faster or slower than nominal line speed, you just have to leave empty slots in the timetable for that. In other words, line capacity takes a hit.

    adirondacker12800 Reply:

    Takes a hit when they switch from the main track to a siding or from the express to the local too. 4 to 8 “slots” depending on signal system and how you want to count slots.

    Peter Reply:

    Note though, that the Authority is now studying a shared-track alignment in Socal based on a request from the local governments. The 87-280 alignment was actually suggested by the San Jose City Council. This was in addition to the 3-track, deep tunnel, and shallow tunnel suggestions. Unlikely that the city will now go back and say “Yes, please, figure out a way to route the trains through Gardner, after all.”

  16. timote
    Jun 15th, 2010 at 15:59
    #16

    Rafael-

    Thanks for this. I don’t think it will fly politically cause I think it is a compromise that nobody wants (the NIMBY’s don’t really want to minimize the four tracking, they just want status quo and the transit buffs don’t want the reduced service levels), but it’s fantastic to think about these things and put them out for intelligent people to consider.

    Thanks!

    rafael Reply:

    I think most people would quite like to see reduced cost, though. Also, staying at two tracks through e.g. Atherton would eliminate a major NIMBY hazard. You may be underestimating just how many additional complaints actual construction is going to generate.

    Wrt to reduced service, transit advocates need to consider that Caltrain is slowly going down in flames as it is. What I’m suggesting would permit substantially increased high-quality service to those stations that contribute 95% of current ridership plus HSR. Advocating solutions that cost hundreds of millions more just to maintain service for the other 5% ought not to fly politically, either.

  17. Andy M.
    Jun 16th, 2010 at 01:50
    #17

    I am rather alarmed at the prospect that high speed rail could basically end freight operations on the peninsula. With peak oil looming and an end to carbon dependency in sight, I believe we are heading for a renaissance of rail freight just as much as we are heading for a massive growth in passenger rail. Taking out freight paths is not setting the right precedent here. Surely there must be another way? If superelevation on curves is a problem, how about using tilting trains instead and so preserving accessibility for freight. How about electric locomotives for freight?

    rafael Reply:

    I’m all for rail freight, but only where it makes sense.

    Oakland to Chicago and Seattle? LA/Long Beach harbors to Chicago, New Orleans and Seattle? Sign me up. If that means CHSRA has to stay out of UPRR’s hair in the Central and Antelope valleys, so be it.

    Port of SF to Santa Clara? Not so much. It’s a secondary line that SP sold to PCJPB in 1991 because it would otherwise have had to shut down passenger rail operations. Since then, freight volume has, if anything declined even further. It’s still a useful little earner for UPRR now that it doesn’t have to fully fund the maintenance of the infrastructure. However, it’s fair to ask if the tax revenue generated off UPRR’s operations in the peninsula plus the activities of its customers there bears any relation to the additional cost and environmental impacts required to maintain freight service in its present form.

  18. Stuart Kaufman
    Jun 16th, 2010 at 13:41
    #18

    This plan reminds me of the “let’s build it cheap” mentality with which San Francisco’s Muni Underground was first constructed. That led to a stub end terminal at The Embarcadero, with no storage capacity, and resulted in constant, sometimes lengthy delays, as trains trying to enter the station waited for others to leave.

    Firebird, if built, would be a mess waiting to happen. Never mind that it eliminates a lot of stations and makes it harder for many people to use public transit. Worse, it requires trains to operate with a precision that we’ve never seen in this country, and are unlikely to see. And if it turns out that we still don’t see precise schedule adherence after the line is already built, we’re going to be stuck with a major mess for many years to come. Sorry Rafael, but you’ve got to make allowance for ordinary human shortcoming and build at least some redundancy into the system, not to mention adequate planning in the first place. This one may be an engineer’s dream, but it’d be a rider’s nightmare. It’s gonna have to be four tracks north of San Jose.

    rafael Reply:

    “makes it harder for many people to use public transit”

    For 5% of Caltrain ridership, i.e. less than 800 people on an average weekday. That’s not “many”. The other 95% would be served with faster service, level boarding and more frequent trains.

    “it requires trains to operate with a precision that we’ve never seen in this country, and are unlikely to see”

    Caltrain operates to a timetable today. For Firebird, it wouldn’t be necessary to fully exploit the capabilities of ETCS level 2 on day one. For example, you could start with a headway of 2.5 or 3 minutes and tighten it up to 2 minutes if and when you’re confident you can stick with the schedule and you need the extra line capacity.

    The notion that no-one the US could never learn from rail operators in other countries makes no sense to me. If the Swiss can do it, why should the US “never” be able to it. Yes, there will be a learning curve, but Americans are just as capable as everyone else in the world.

  19. Andy M.
    Jun 18th, 2010 at 05:15
    #19

    Sorry Rafael, but the Swiss don’t do this. Where stoppers and expresss share tracks, it’s only where there is significant excess capacity (ie, rural areas, where the local services aren’t that frequent). Wherever things get tight, such as on approaches to major cities such as Zurich and Berne, lines are triple or quadruple tracked permitting fast and slow services to be segregated and keep out of one another’s way. With the exception of one or two short sections, the Zurich to Berne main line is at least 4 track throughout (when alternative and parallel routes are taken into account) and it’s not always predictable which of those routes any given non-stop train will take. Timekeeping precison alone does not make for good overall timekeeping. the second ingedient is reserve capacity and redundancy.

Comments are closed.